GG asked ... Fix food processor motor?    |    T asked ... How do I turn the delay off on Electrolux DX302 dishwasher?    |    Helen asked ... How can I mend my Kenwood Gourmet FP505?    |    Roy Turner asked ... Kohlangaz Gosford HE fire?    |    Peter asked ... How can I mend a Powerwasher PRO PRO1800PWE?    |    Click here to ask your question

gutting and refurbishing a house?

just inherited a small house that needs total renovation, im no expert so need some good sound advice.
my plan is to rip the old bathroom kitchen out and strip the walls completely then rewire, replumb then fit the bathroom after tiling and kitchen after tiling when the new plumbing and electrics are in then plaster the other rooms after plumbing and electrics are in and finally the doors skirtings last off.
Is this the right order to do things in?
chester, September 2008
you fit the bath plumb it up hot and cold pipes and also the drainage pipes and then tile it.You fit the kitchen first and then you tile it.You do the electrics first which is the first fix put the wires in and put the back boxes on and then plaster it and then you do the second fix which is putting the switches,lights and sockets on and then you do the plumbing and then you can do the doors and skirting.

paki_maffia_949@hotmail.com

MO, October 2008