GG asked ... Fix food processor motor?    |    T asked ... How do I turn the delay off on Electrolux DX302 dishwasher?    |    Helen asked ... How can I mend my Kenwood Gourmet FP505?    |    Roy Turner asked ... Kohlangaz Gosford HE fire?    |    Peter asked ... How can I mend a Powerwasher PRO PRO1800PWE?    |    Click here to ask your question

how can i fix a crack in my lead valleyon my roof?

i have got a crack in the lead valley on my roof how can i fix this andnot have to take all the the roof off .
norman oxton, October 2006
Silicone sealant sticks to lead very well, use low modulas clear or special silicone for lead, Stick a patch of lead on top off the crack should last for years but is a bodge job

Dave, May 2007
Completely renew the valley, and layboards if damaged.
The lead should be minimum code 4 with an ideal width of 390mm laid in 1.5m lengths with a 150mm lap to allow for movement the lead should be secured at the top only with copper nails.
In addition to the layboards ensure there are tilt edges fitted.
The width of the cut valley should be approx 4 to 5 inches.

mal, October 2006
Buy a lead roll from local supplier, about 9inch wide roll should do.

Retired Jobbing builder. The following was a choice customers had because of the cost of renewal. Proceed as follows.
A bodge job. cut a strip of 3ply felt and mastic over the split.
A really bodgy job is Aquaseal No 5 about 3 coats on the whole valley, but it only lasts about 2yrs if that.


A better and firmer repair would be.

Mark the CUT slates/tiles either side of the valley at two rows above and two rows below the split. Remove the cut slates/tiles. Cut from the roll of lead a strip the same width as the valley lead. Cut the split across the valley and gently lift the top part just enough to slide the patch piece under about 3inches. on the bottom lay a layer of bitumen/mastick [thick stuff] then tap the lead patch down onto the bitumen/mastic that will hold it in position. You have a reasonably neat repair.
Replace the slates/tiles.
I've done many like it and it extended the life of valleys for ages before they finally had to have new zinc pre-formed valleys. Warning you need to number or letter each cut slate/tile so they go back in the same spot they were cut for. If you don't then you'll have a puzzle on your hands believe me. Post how you got on when you've done it.